Monthly Archives: October 2013

Happy anniversary!

We first laid eyes on the property exactly one year ago yesterday (10/13/12).

We are ready to close in the walls. The insulators come tomorrow and the drywallers come later this week (after we pass insulation inspection). Then it’s time for floors, trim, tile, etc.

Another big step we are hoping for in the next few weeks is a finished shed and approval to energize.

Here are some pictures.

We had the vents installed. Here is the range hood.

20131013-104556.jpg

The “foam” from the foam and caulk. We passed the air seal inspection.

20131013-104603.jpg

Our floors were delivered from the mill one town over.

20131013-104611.jpg

The deck frame is in.

20131013-104622.jpg

The shed.

20131013-104628.jpg

Last but not least, my brother, Mac, came to visit a couple weeks ago.

20131013-105250.jpg

We passed inspection!

Now we are working on getting everything else ready for insulation and drywall. That means we have several subcontractors coming this week and next. Then, it will be time to start flooring and tiling.

Here are some pics of the last couple of weeks.

20131007-180547.jpg

20131007-180602.jpg

20131007-180617.jpg